h1. Trac Organisation
3
4 1 mehdi
To perform a better use of this trac and make it Understandable for all, a charter of use has been defined.
5 17 mehdi
6 1 mehdi
This trac had to be used because it is the central tool to define the priorities of development and to follow the Openspace3D project. 
7
8
9 18 mehdi
h2. milestones
10
 
11
12 1 mehdi
A milestone corresponds to a version of Openspace3D and the corresponding voyager.
13 5 mehdi
14 1 mehdi
The "Openspace3D beta" milestone permits to define the global objectives concerning the platform.
15
16
17 18 mehdi
h2. Components
18
19
20 1 mehdi
They allow to identify which components is targeted concerning a corresponding tickets.
21
22
A ticket could concern several components especially for Openspace3D beta tickets
23 17 mehdi
24 18 mehdi
25
h3. Example
26
27 13 mehdi
VM_SO3Engine: 3D Engine Component(SO3Engine)
28 17 mehdi
29 2 mehdi
It could concern a development to modify SO3Engine.dll or to add a functionality into it
30 1 mehdi
31
ex : Add functions to use stereoscopic rendering
32
33
OS3D_PlugIT : Component conerns the development of a new plugIT or a modification of an existing plugIT
34
35 2 mehdi
36 18 mehdi
h2. Naming Tickets
37
38
39 1 mehdi
The objetive is to define tickets as thematic tickets.
40
41 8 mehdi
It optimises the project management.
42 1 mehdi
43
44 18 mehdi
h3. Example
45
46
47 17 mehdi
[Particles] Integration of particles system in Openspace3D (it is a global ticket) 
48 16 mehdi
49 1 mehdi
50 18 mehdi
h2. A concrete example
51
52
53 8 mehdi
The following example shows and explains the naming for tickets corresponding to a functionality.
54 1 mehdi
55
- "We want to develop an Avatar plugIT into Openspace3D"
56
57
- The global tickets in Openspace3D beta milestone is :
58
59 18 mehdi
_milestone_ : Openspace3D beta _summary_ : [Avatar] Add a plugIT to manage avatar. _components_ : VM+OS3D_plugIT
60 1 mehdi
61 5 mehdi
- Into the milestone corresponding to the implementation, we add all "subTickets" corresponding to Avatar plugIT project : 
62 1 mehdi
63 18 mehdi
_milestone_ : Openspace3D alpha 0.1.9 _summary_: [Avatar] Management of bones into 3D Engine _Component_ : VM_SO3Engine
64 8 mehdi
65 18 mehdi
_milestone_ : Openspace3D alpha 0.1.9 _summary_: [Avatar] Possibility to Add Mesh to a bone into 3D Engine _Component_ : VM_SO3Engine
66 8 mehdi
67 18 mehdi
_milestone_ : Openspace3D alpha 0.1.9 _summary_: [Avatar] plugIT editor _Component_ : OS3D_plugIT
68 1 mehdi
69 18 mehdi
_milestone_ : Openspace3D alpha 0.1.9 _summary_: [Avatar] Animation system _Component_ : OS3D_plugIT
70 1 mehdi
71 18 mehdi
72
h3. Why used this topology?
73
74 8 mehdi
75 17 mehdi
* The global functionality is defined by a project ex : [Avatar]
76 8 mehdi
77 17 mehdi
* The functionallity is cutted in several tickets for the development concerning a particular version of Openspace3D
78 8 mehdi
79 17 mehdi
* Openspace3D beta allow to have a global vision of the final project and a vision of the priorities